Banner-blog--top-shape
chevron-green

2025 Year in Review

ByTara Ekren /

The Metro Flood Diversion Authority has released it’s FM Area Diversion project year-end construction update for 2025.

 

If you combined the concrete, asphalt and riprap placed and the material moved for the project in 2025, it would be enough to fill the North Dakota Capitol Building three times! The piling, if laid end-to-end, would stretch more than 42 miles! The project, which will provide permanent flood protection for nearly 260,000 people, expects to complete major construction next year while shifting completed components to an operations and maintenance phase.

 

One component of the stormwater diversion channel is 19 road and rail bridges. To date, 14 bridges are complete and open to traffic. The asphalt used for the bridges so far would be enough to construct a 4-foot wide bike path that stretches roughly 300 miles.

 

You can watch the Authority’s year-in-review video or get the latest construction updates in the newest drone construction update video.

 

Here are some facts and figures of all the work completed in 2025 across the entire project:

blog-bottom-shape
chevron-up

MORE NEWS

Rendering of county road bridge over the stormwater diversion channel
Temporary Lane Closure Planned
A temporary lane closure is planned for County Road 22, located southwest of Harwood, North Dakota, on the bridge across...
Milestone Achieved: Maple and Sheyenne Rivers Now Flowing through Aqueducts
In a historic moment for the FM Area Diversion Project, the Sheyenne River was rerouted through its aqueduct structure on...
Rendering of county road bridge over the stormwater diversion channel
Temporary Lane Closures Planned
Ongoing construction of the stormwater diversion channel portion of the FM Area Diversion project necessitates various single lane closures on...
Scroll to Top