I-94 Ramp Opening Delay

ByTara Ekren /

Contact
Tara Ekren, PIO
Red River Valley Alliance
701-306-3294 (cell)  |  pio@rrvafm.com 

 

 

Originally planned to open on Sunday, the westbound on-ramp to I-94 and eastbound off-ramp from I-94 at Exit 342/Raymond Interchange openings have been delayed. Crews are working to have the westbound on-ramp and Weigh Station open on Tuesday, June 18, and eastbound off-ramp on Thursday, June 20.  

 

 

Existing detours will remain in effect. Traffic that would normally use the on-ramp to access westbound I-94 at the Raymond Interchange will need to follow the marked detour route north of I-94 by traveling west on County Road 10 to County Road 15 to the on-ramp. 

 

 

Eastbound I-94 traffic that would normally use the off-ramp at Exit 342 will be directed to exit prior at County Road 15/Exit 340 and follow the marked detour route north of I-94 by traveling north on County Road 15, then east on County Road 10 to 38th Street NW. 

 

 

During these ramp closures the I-94 WB Weigh Station will also be closed.  

 

 

Motorists are asked to exercise caution and patience in the construction area during this closure and allow for additional travel time the detours may cause.  

 

 

For more information about the FM Area Diversion project, visit www.fmdiversion.gov

blog-bottom-shape
chevron-up

MORE NEWS

I-94 Ramp Closures Begin Sunday, June 9
Contact Tara Ekren, PIO Red River Valley Alliance 701-306-3294 (cell) | pio@rrvafm.com   Construction is progressing on the I-94 bypass...
ASN Constructors Gives Back as part of Construction Safety Week
Contact Tara Ekren, PIO Red River Valley Alliance/ASN Constructors 701-306-3294 (cell) | pio@rrvafm.com     FARGO, N.D. – ASN Constructors...
Interstate 94 Lane Closures Begin
Contact Tara Ekren, PIO Red River Valley Alliance 701-306-3294 (cell)  |  pio@rrvafm.com      FARGO, N.D. – Work will begin...
Scroll to Top