Second Railroad Bridge Opens

ByTara Ekren /

A second railroad bridge over the stormwater diversion channel of the FM Area Diversion project is complete and has been put in service. As of Wednesday, November 12, 2025, BNSF Railway trains are now traversing the new bridge on the Prosper subdivision line.

 

The railroad bridge is on the northwest edge of Fargo, north of the County Road 20 crossing and east of County Road 13.

 

The bridge measures 405 feet long. Construction began in the summer of 2023 to construct a temporary track, called a shoofly, where trains operated until the new bridge was constructed. Work began on the bridge structure in 2024 and was completed by ASN Constructors and Kraemer North America in partnership with BNSF, which constructed the track. BNSF will own and maintain the railroad bridge.

 

For more information about the FM Area Diversion project, visit www.fmdiversion.gov.

 

Contact
Tara Ekren, PIO
Red River Valley Alliance
701-306-3294  |  pio@rrvafm.com

blog-bottom-shape
chevron-up

MORE NEWS

Rendering of county road bridge over the stormwater diversion channel
Temporary Lane Closure Planned on County Road Bridges
Ongoing construction of the stormwater diversion channel portion of the FM Area Diversion project necessitates two separate single lane closures...
Controlled Burn Planned
A controlled burn is planned within the stormwater diversion channel right of way southwest of Harwood beginning at approximately 8:30...
Controlled Burn Planned
A controlled burn is planned within the stormwater diversion channel right of way northwest of West Fargo beginning at 8:00...
Scroll to Top